C03 Bridge – New Alamein City.

>>

>>

C03 Bridge – New Alamein City.

Owner
Consultant

Josour Consultant Engineering (JCE)

Contractor

Concord for Engineering & Contracting

Location

Alamein City, EG

Status

Completed

Completion Date

-

Project Overview

The bridge forms a vital connection along the high-speed rail alignment and features a hybrid structural system consisting of: Pre-cast concrete beams and Steel bays The total length of the bridge segment is 350 meters, with a deck width of 28.6 meters, ensuring high capacity and structural efficiency.

Our Role
As the Structural Designer and Engineering Consultant for the executing contractor, JCE’s scope included: 1-Structural design and analysis 2-Planning and coordination 3-Preparation of all structural design and construction drawings 4-Full technical support throughout execution
Gallery Project